Provision of Compression Services-Phase V Project for TDE/Tatweer Petroleum

Project Background:

As part of Tatweer Petroleum’s field development plan, to provide an immediate solution, both technical and economical, that satisfies the urgent needs of Tatweer Petroleum for gas compression capacity to carry out its current production plans, Tatweer Petroleum decided to install two trains of rental compressor stations with 10 x 25 mmscfd compressors in each unit. The Engineering, Procurement & Construction (EPC) Contractor was TDE Overseas Ltd. The Project execution started in March 2020 and completed by February 2021.

Project Scope & Highlights:

Project scope includes Civil, Mechanical, Structural, Piping, Electrical & Instrumentation, Painting and Commissioning Assistance

  • Project Duration: 11 Months (Mar. 2020 to Feb. 2021)
  • Man-hours: 304,912 Hours, without LTI.
  • Concrete Works: 2,470 Cu. M.
  • Excavation Works: 3,328 Cu. M.
  • Piping and Welding: 17,680 Inch Dia.
  • Structural Steel Fabricated & Erected: 44.540 Tons.
  • Equipments Erected: 74 Nos
  • Total Area Painted: 3,400 Sq. M
  • Electrical Cable Laid: 18,500 M
  • Instrument Cable Laid: 13,500 M