Replace LSFO Blast Proof Substation Project for Bapco
Project Background:
As part of replacing BAPCO’s LSFO Complex, the construction of new blast-resistant elevated Substation Project was awarded to MCSC. The Engineering, Procurement & Construction (EPC) Contractor was JGC Gulf International Co. Ltd.
Project Scope & Highlights:
Project scope include civil, substation building, mechanical, structural, electrical, fire- protection & painting works which involves switch gear room, generator bays, transformer bays, EDG building, battery room, power cable laying, installation of lighting fixtures, installation of earthing & grounding, lightings.
Project Duration: 15 Months (Jan. 2015 to Apr. 2016)