ALBA Line 6 GAP E&I Erection Project (November 2018)

Project Background:

As a part of ALBA’s Line 6 expansion, Fives Solios awarded Green Anode Plant (GAP) E&I Erection project works to MCSC.

The Green Anode Plant contains 6 main areas:

  • Coke Area
  • Carbon Recycling Unit
  • Paste Plant
  • Cooling Tunnel
  • Pitch HTM Facilities
  • Electrical Substation which involves installation of Switchgears and all associated Electrical Equipment

Project Scope & Highlights:

The project scope involves installation of Electrical Equipment, Panels, Instruments, Cables, Lighting, Outlets, Cable Trays, Earthing, Lightning and support works.

Electrical substation was a two storey concrete building of 35M L X 25M W X 9M H.

  • Duration: 12 Months (November 2017 to November 2018)
  • Man-hours: 326,614 Hours, without LTI
  • Equipment Erected: 709 Nos.
  • Electrical Cable Layed: 116,120 M.
  • Instrument Cable Layed: 25,925 M.