Blast Proof Extension of Laboratory Building at CGP-II

Project Background:

This project was executed as part of extending the existing Banagas Building at CGP-II. The main scope involves extending the existing laboratory building fitted with latest Lab Equipment and Furniture. Apart from major building civil works all associated Structural, Electrical, Instrumentation and HVAC work were also carried out as part of the project scope. It also involved demolition, re-routing, modification and extension of the existing facilities to ensure proper interconnection with existing building and commissioning of the new building.

Project Scope & Highlights:

The scope of work for this project includes Civil, Building, Structural, HVAC, Electrical, Instrumentation, Painting, Commissioning works.

  • Duration: 12 months (May 2018 to May 2019).
  • Man-hours: 115,148 Hours, without LTI.
  • Block works: 444 M2.
  • Rebar Works: 77.05 Tons.
  • Waterproofing: 285 M2.
  • Area Painted: 2432 M2.
  • E&I cabling: 5100 Sq. M.
  • Tubing works: 1800 Sq. M.
  • HVAC: 3 HVAC Units with ducting, Blast Dampers and other ancillaries