This project was executed as part of extending the existing Banagas Building at CGP-II.
The main scope involves extending the existing laboratory building fitted with latest Lab Equipment and Furniture. Apart from major building civil works all associated Structural, Electrical, Instrumentation and HVAC work were also carried out as part of the project scope.
It also involved demolition, re-routing, modification and extension of the existing facilities to ensure proper interconnection with existing building and commissioning of the new building.