Installation of 3 Nos of Skimming & Treatment Stations Project for STAS/ALBA

Project Background:

STAS-Canada was the EPC Contractor and awarded this project to MCSC.
Project scope includes Civil Works, Mechanical Installations per station involves TAC and Skimmer Columns with Bottom and Top Arm, TAC Module, Skimming Module, Feeding Systems (AIF3), Sampling and Operation Platforms with stairs, Drip Plates, Dross Chamber, Weigh bridges (2), Pneumatic system and piping, Traffic guides and station access barriers, Supports for crucible positioning instruments, Dust collector, Fan, Ducting, Stack and related Platforms, Hydraulic Unit, Emergency Hydraulic Power Unit (EHPU), Supports for hydraulic lines, Machine guarding and Bollards, Traffic lights, Control-room cabin with HVAC system, Electrical and Instrumentation Works and Painting Works

Project Scope & Highlights:

  • Project Duration: 14 Months (April 2018 to June 2019)
  • Man-hours: 98,434 Hours, without LTI.
  • Ducts and Chutes Installed: 6 Tons
  • Structural Steel Erected: 31 Tons.
  • Equipments Erected: 23 Nos
  • Total Area Painted: 1,221 Sq. M
  • Power & Earth Cable Laid: 11,831 M
  • Control Cable Laid: 4,255 M
  • Cable Glanding & Termination: 816 Nos