SKID FABRICATION FOR 2 NEW WELL MANIFOLDS

Project Background:

Bapco Upstream has undertaken a project to install two New Well Manifolds, WM 32 and WM 33, comprising a total of 30 skids. Thermodynamics Engineering (TDE) serves as the EPC contractor for this project, with MCSC as the Subcontractor for the Fabrication & Construction scope. The project commenced in February 2023, with a targeted completion date set for mid-2025.

Project Scope & Highlights:

Header Modular Skid, PSV Platform, Test Separator-1, Test Separator-2, Production Separator, Fuel Oil, are all included in this project.

Project Duration: Feb 2023 – June 2025

Well Manifold-32

  • Piping works: 17,234 Inch Dia.
  • Structural Steel Works: 171 Tons
  • Total Area Painted: 10,044 Sq. M

Well Manifold-33

  • Piping works: 17,234 Inch Dia.
  • Structural Steel Works: 171 Tons
  • Total Area Painted: 10,044 Sq. M