Replace LSFO Blast Proof Substation Project for Bapco

Project Background:

As part of replacing BAPCO’s LSFO Complex, the construction of new blast-resistant elevated Substation Project was awarded to MCSC. The Engineering, Procurement & Construction (EPC) Contractor was JGC Gulf International Co. Ltd.

Project Scope & Highlights:

Project scope include civil, substation building, mechanical, structural, electrical, fire- protection & painting works which involves switch gear room, generator bays, transformer bays, EDG building, battery room, power cable laying, installation of lighting fixtures, installation of earthing & grounding, lightings.

  • Project Duration: 15 Months (Jan. 2015 to Apr. 2016)
  • Man-hours: 715,222 Hours, without LTI.
  • Concrete Works: 2,825 Cu. M.
  • Excavation Works: 8,979 Cu. M.
  • Asphalt & Paving Works: 5,268 Cu. M
  • Rebar Works: 250 Tons.
  • Structural Steel Fabricated & Erected: 26 Tons.
  • Total Area Painted: 850 Sq. M
  • Rooms/Buildings: 3 Nos.