T&I SHUTDOWN WORKS FOR CENTRAL GAS PLANT – TRAIN III

MCSC successfully completed the Bapco Gas T&I Shutdown Works at CGP3 in January 2024. The project, awarded in September 2023, involved 231-line items, including major equipment installation and valve repairs. Despite the complex scope, MCSC completed the turnaround within 18 days ahead of schedule. During the peak, the Shutdown manpower was 730 and the total man-hours completed was 155,000 manhours maintained a high level of safety standard and without any Loss Time Incidents

Project Highlights:

Project scope includes T&I Shutdown Works of 101 Major Equipment’s like Columns, Vessels, Reactor, Heat Exchanger, Heaters, Tank, Flare Stack, Revamp works

  • Project Duration: 6 months (September 2023 to February. 2024)
  • Shutdown duration: 18 Days - Round the clock basis
  • Man-hours: 155000 Hours, without LTI
  • Peak manpower per day: 730 Nos
  • Total Equipment Installed: 101