T&I SHUTDOWN WORKS FOR CENTRAL GAS PLANT – TRAIN III
MCSC executed a major Shutdown Hub 1 in BAPCO, a Maintenance Project for the Turnaround and Inspection of 12 operating units in the refinery. Hub-1 Shutdown was one of the most complex T & I work executed in BAPCO.
Project Highlights:
Project scope includes T&I Shutdown Works of 101 Major Equipment’s like Columns, Vessels, Reactor, Heat Exchanger, Heaters, Tank, Flare Stack, Revamp works
Total man-hours: 250,000 without LTI
Duration: 19 August 2022 to 19 October 2022
Major jobs executed by MCSC during the T&I are given below.