T&I SHUTDOWN WORKS FOR CENTRAL GAS PLANT – TRAIN III

MCSC executed a major Shutdown FCCU Complex T & I in Bapco, a Maintenance Project for the Turnaround and Inspection of 9 operating units in the refinery. FCCU Complex was one of the most complex T & I work executed in Bapco.

Project Highlights:

  • Duration: 18 May 2021 to 06 July 2021
  • Total man-hours: 146,070 without LTI

Major jobs executed during the T&I are given below.

  • FCCU (2 Columns, 25 Vessels, 1 Heater, 1 Regenerator, 1 Reactor, 11 Misc. Assets, 5 RV’s, 5 CV’s, 37 Orifices, 30 Thermowells, 29 Check valves, 4 Annubars)
  • 5CDU (2 Columns, 6 Vessels)
  • 2POLY (3 Columns, 7 Vessels)